Construction Team:
Contract Manager: John Zerkee / Superintendent: James Hanninen
M.D. Of Clear Hills
Two 3 Span Bridges - MD of Clear Hills
The MD of Clear Hills required the construction of two 3-span bridges and 3 kms of new rural road. The roadwork was sub-contracted to Central Peace Contracting.
Both the roadwork and the bridge work were carried out at the same time so as to save on any extra mobilization costs. Construction of the bridges progressed well but, early in the job, rain held up the roadwork. The job was able to get back on schedule as the weather improved allowing the project to be completed on time.
The owner appreciated the quality of the work and the timely manner in which it was completed even though weather caused delays.